Are we on time? Sonja put in a fair amount of effort to document the project plan I had in my head. The following summary shows the planned schedule, updated as of March 2008.
Start Date: |
Thu 01/05/03 |
Projected Finish Date: |
Sun 06/03/11 |
Name |
Start |
Finish |
% Complete |
Start Project |
Thu 01/05/03 |
|
100% |
Planning |
Thu 01/05/03 |
Wed 28/05/03 |
100% |
Design |
Thu 29/05/03 |
Sun 03/08/03 |
100% |
Factory |
Thu 19/06/03 |
Wed 03/11/04 |
100% |
Hull |
Thu 04/11/04 |
Sun 01/06/08 |
85% |
Mechanical |
Sat 07/04/08 |
Sun 5/10/08 |
4% |
Interior |
Mon 6/10/08 |
Sat 4/09/10 |
0% |
Exterior |
Sun 5/09/10 |
Fri 21/1/11 |
0% |
Launch |
Sat 22/1/11 |
Sun 6/3/11 |
0% |
Project complete |
|
Sun 6/3/11 |
0% |